01 / PLANNING NOTES
Measure each run
A rectangle’s perimeter is the sum of two widths and two lengths. For irregular plots, record each side separately. On a slope, a horizontal plan measurement can differ from the installed run.
02 / PLANNING NOTES
Mark gate openings
Gate openings reduce the wire or panel length, but the gate still needs supports and connections. Record the side and the position of each gate.
03 / PLANNING NOTES
Count shared corners correctly
A corner is shared by two neighbouring runs. Counting it twice, or omitting it, gives the wrong post total. Check run ends and gate posts separately.
04 / PLANNING NOTES
Confirm the estimate on site
The Boundary Planner explores these relationships in a preliminary plan. Default spacings are calculation inputs, not confirmation of product suitability. Final quantities require site measurements and the actual selected product dimensions.